Brick Work

Home Interior Decorating Exterior Site Pictures Status Reports Planning Archive

Up
Landscaping
Carpet & Tile
Decks & Lights
Deck!
Kids at the house
Mantle!
Kitchen looks great!
Closets and Countertops
Railings
Ceramic Floors
Trim Carpentry
Up-to-Date View
Cabinets
Mudding Started
Drywall Started
Joint Compound
Brick Work
Insulation
Insulation Started
Brick
Roofing
Plumbing
Hardy Board
Windows
Barrel Ceiling
Roof Paper
Roof Structure
Rest of Trusses
Second Floor Walls
Second Floor Started
First Trusses
Main Level Walls
Walls Going Up!
Main Level Floor
Floor Joists
Framing Started!
Delivered Lumber
Compacted Dirt
Rough Grading
Basement Slab
Foundation Sealed
Drains Roughed-In
Poured Foundation
Foundation Forms
Utility Access
Poured Footings
Footings
Huge Hole
Empty Lot

 

March 27, 2007

Brick work continues!

Click on an image to see the full-size version.
20070327house01.JPG (122500 bytes) 20070327house10.JPG (107460 bytes) 20070327house09.JPG (124204 bytes)
The front of the house is done They're doing some re-work on this corner--not quite sure what this is about. They're finishing up the back of the house.  The "day to day" lines are pretty obvious, but we're assuming they won't be once the mortar all dries.
20070327house08.JPG (54990 bytes)    

Drywall delivery

Drywall was being delivered while we were there.

20070327house04.JPG (104704 bytes) 20070327house02.JPG (116797 bytes) 20070327house07.JPG (118967 bytes)
Insulation was being worked on. A truck full of drywall. They brought the upstairs drywall in through the window.